Transmission Elements Outage Report for  27-Sep-2022
 
A. Details of Transmiss                    ioPlanned Outage n Elements under Planned Outage:-
Sl NoSub-Station/LineCategoryOwner NameOutage DateExpected Revival DateRevival DateReason/Remarks
1PAPPANKALAN-I 66/11kV, 20MVA Tx-II 66/11kV TransformersDTL12/09/2022 14:1029/09/2022 18:00 OVERHAULING.
2INDRAPRASTHA POWER 220/33kV 100MVA Tx-III220/33kV ICTsDTL27/09/2022 08:50 27/09/2022 10:50HOT POINT
3BAMNAULI 400/220kV 315MVA ICT-IV400/220kV 315MVA ICTDTL27/09/2022 17:15 27/09/2022 20:48AT MEHRAULI : HOT POINT.
4MEHRAULI 220/66kV 100MVA Tx-I220/66kV ICTsDTL27/09/2022 18:05 27/09/2022 19:32AT PARK STREET : HOT POINT.
5220kV BAMNAULI-PAPPANKALAN-III CKT-II220 KV LINEDTL27/09/2022 10:01 27/09/2022 14:32AT BAMNAULI : TAN DELTA TESTING.
6220kV Harsh Vihar - Preet Vihar Ckt-II220 KV LINEDTL27/09/2022 10:50 27/09/2022 12:26AT HARSH VIHAR : GAS LEAKAGE.
7220KV GAZIPUR - MAHARANIBAGH CKT. -I220 KV LINEDTL27/09/2022 14:15 27/09/2022 19:35AT MAHARANI BAGH : NCRTC WORKS.
8220kV BAMNAULI-PAPPANKALAN-III CKT-I220 KV LINEDTL27/09/2022 14:42 27/09/2022 16:51AT BAMNAULI : GEN MTC.
9220kV DIAL- MEHRAULI CKT-I220 KV LINEDTL27/09/2022 17:15 27/09/2022 20:48AT MEHRAULI : HOT POINT.
10220kV PRAGATI - PARK STREET CKT-I220 KV LINEDTL27/09/2022 18:05 27/09/2022 19:32AT PARK STREET : HOT POINT.
 
B. Details of Transmission Elements under Forced Outa    ge:-Forced Outage
Sl NoSub-Station/LineCategoryOwner NameOutage DateExpected Revival DateRevival DateReason/Remarks
1VASANT KUNJ 220/66kV 160MVA Tx-I220/66kV ICTsDTL27/09/2022 12:30 27/09/2022 16:28BUS BAR PROTECTION OPERATED.
2VASANT KUNJ 220/66kV 100MVA Tx-II220/66kV ICTsDTL27/09/2022 12:30 27/09/2022 13:20BUS BAR PROTECTION OPERATION
3VASANT KUNJ 220/66kV 100MVA Tx-III220/66kV ICTsDTL27/09/2022 12:30 27/09/2022 13:20BUS BAR PROTECTION OPERATED.
4PATPARGANJ 220/33kV 100MVA Tx-III220/33kV ICTsDTL27/09/2022 14:29 27/09/2022 17:40AT SARITA VIHAR : DIST PROT, ZONE-I, R PHASE.
5220kV WAZIRABAD - KASHMEREGATE CKT-II220 KV LINEDTL27/09/2022 12:30 27/09/2022 16:28BUS BAR PROTECTION OPERATED.
6220KV WAZIRABAD - MANDOLA CKT-I220 KV LINEDTL27/09/2022 12:30 27/09/2022 13:20BUS BAR PROTECTION OPERATION
7220KV WAZIRABAD - MANDOLA CKT-II220 KV LINEDTL27/09/2022 12:30 27/09/2022 13:20BUS BAR PROTECTION OPERATED.
8220kV MAHARANI BAGH - SARITA VIHAR CKT220 KV LINEDTL27/09/2022 14:29 27/09/2022 17:40AT SARITA VIHAR : DIST PROT, ZONE-I, R PHASE.
C. Details of Transmission Elements Opened manually due t       o H igh Voltage:-